SAB PROGRESS
Construction works are progressing for the new bank headquarter for SAB in Leipzig. Due to the high ground water table, extensive piling works were needed to create a watertight box extending 40m below ground. This has allowed for the demolition of the 3m thick Robotron foundations that had previously remained stuck in the ground below the water. With all demolition now completed, works have finally commenced on the new basement slab, and the cores are scheduled to rise in February.