MINORIES RESIDENTIAL
The concrete frame of Minories residential building has finally reached topping out. The 16th floor of the building was poured in the second week of January. Eleven levels of precast stairs have been installed on site with the rest to follow in the next two weeks. Scaffolding will rise from February with the facade scheduled to commence installation in May 2019.
The forward and backward stepping of the concrete frame allows for the maximum in development area while minimising overlooking and overshadowing of adjacent spaces.